The building is going up

The contractors officially started work in mid January but already by mid April, the foundations are finished and the walls are up. The roof rafters are in progress.

Block and beam floor

The front door will be in the middle.

The two roof ridges are steel

The smaller black shape in the lower right above is the foundation for the plant shed where the machinery for the borehole will be sited.